Business Process Re-engineering (BPR) inevitably involves change. However, modern business organizations are extremely complex. Setting improvement targets in BPR too high without considering the company’s capability and its external and internal interactions will have little chance of achieving the set targets, which means project failure. Unfortunately, forecasting of the BPR outcomes is currently a wild guess to management. This paper describes a risk model that estimates a process improvement capability score and integrates with a performance effectiveness function to assess the likelihood of meeting performance gain targets from process improvement projects undertaken by companies. The risk assessment can assist management to set more realistic performance gain targets for process improvement projects with a better chance of success.
Business process re-engineering (BPR) for new business processes or change of existing processes is not an ad-hoc activity. It requires a good project management approach to coordinate and decide on a range of factors in a structured manner [
A successful BPR project depends on the capability of the company implementing it. A proper analysis of known success and failure capability factors can reduce the risk of failure and increase the likelihood of success. The structured process improvement framework proposed by Rohleder et al. [
This paper outlines a risk assessment method to assist organisations re-engineering their business processes in order to achieve the expected performance gains. The innovation of this method is the ability to estimate the probability of meeting a desired target performance level at various points in time. This knowledge is most critical to decision makers to a) compare different BPR projects and execute the project with the highest probability of success over time, and b) form the basis for adjusting the scope and performance targets of BPR projects to achieve a realistic chance of success.
Performance measures are characterized through metrics. Consolidated sets of performance indicators are used by company management to ensure attainment of their objectives and goals linked to strategy and value creation for the company. Prandini et al. [
The problem of setting performance measures has been studied extensively in the manufacturing sector. Ahmed et al. [
In a comparison of eight performance measurement systems (PMS), Garengo et al. [
A thorough risk assessment provides benefit to decision makers coordinating changes in BPR to minimise potential failure and reduce effect of undesirable events. In
different probabilities. It is clear the probability of achieving the initially expected gain Pexp is somewhat over optimistic with a probability of success less than five percent. Instead, if the expected performance is adjusted to Pexp1, the chance of achieving the expected performance is close to half.
Lowering expectation levels is a decision that can be made conservatively and provides the short-term benefit of improving the momentum of improvement. Alternatively on being made aware the probability of success is lower than expected a decision can be made to expand existing capability to cover the gap.
In order to ensure success of operations improvement implementation, the capability of an organisation should be at a level that can handle the complexity of the improvements being attempted and the performance targets being aimed for. In this research, the capability level of an organisation working on a BPR project is evaluated as the capability score SC. This measure is calculated as a function of a set of capability indicators X = { X 1, X 2, …, X n} where the Xi (i = 1, …, n) are known from prior research such as productivity audit. In its simplest form, Xi can be represented as a linear weighted sum as shown in Equation (1).
These performance indicators are selected such that they have a causal link to operations performance and continuous improvement. A nine level rating system is used to normalise the extent of capability for each capability factor to a comparable basis.
To effectively obtain the capability score of an organisation, it is necessary to break down and categorise the individual capability factors so that more accurate assessment of each of the capability factors can be made. This requires an enterprise architecture to form the modelling framework. Mo [
Performance gains are anticipated from a BPR project. These performance gains are measured by a range of individual performance indicators P = { P 1, P 2, …, P m} where the Pi (i = 1, …, m). For the convenience of decision making, the current performance indicators Pcur is a management defined function. In practice, a linear weighted sum is used as shown in Equation (2). Effort required to achieve higher levels of performance often involves greater complexity and cost. A performance effectiveness function kP can be defined as a measure of the perceived effort required to overcome difficulty and complexity to achieve a particular level of performance from the current level P0. Each of these performance outcomes are measured from a performance scale ranging from success (highest score) to failure (lowest score).
The performance of a BPR project can vary between two extremes:
§ A theoretical performance level Pth that can be attained if all capability elements are applied in a perfect manner.
§ The capability elements are not effective and no improvement of productivity has been recorded. This performance level is represented as P0. If the project is not implemented, Pcur = P0.
However, the problem of finding the intermediate relationships between kP and P is mixed with human judgement. One method is to solicit the opinion of the stakeholders involved in the operations improvement project. The Analytic Hierarchy Process (AHP) is applied to consolidate the vector of priority (VP) over the range of P0 to Pth. To assist in making consistent decisions, Equations (3), (4) and (5) are applied in the judgment matrix. For any j = 1 to th (i.e. th = 5 in this illustration and * is the wild card for the row or column elements),
A pairwise comparison judgement process on θkj with a scale of 1 to 9 generates intermediate values of VPj. The performance effectiveness factor kP is obtained over the range 0 to 1 by Equation (6).
Intuitively it is reasonable to expect that having a higher level of capability, the organisation can achieve greater levels of BPR performance gain closer to the theoretical maximum. These curves are obtained by estimating the difficulty levels kP in past improvement projects against the increase in performance P on a particular SC. The derivation of this function is based on published data [
The goal of this research is to predict future performance gain of an operations improvement project based on an estimate of capability for that project. Assuming an estimated SC of 70 for the project (
A risk assessment model has been proposed to assess the likelihood of meeting performance gain targets from BPR projects undertaken by companies. The method indicates to companies when and where their capabilities need to be adjusted to maximize their possible outcomes. This alleviates the problem that organizations have when they embark on BPR initiatives with an organizational setup that limits their chance of success.
An advantage for companies using the SC model is their improvement ambition level can be set more realistically based on knowledge of their estimated capability. The adjusted performance targets are better matched to organizational capability which in turn means a higher hit-rate of successful BPR projects. More success tends to provide positive feedback setting the seeds for sustained continuous improvement. Setting the bar too high too early can demotivate a BPR programme and kill it before it even gets going.
Boyd A. Nicholds,John P. T. Mo, (2015) Risk Assessment of Business Process Re-Engineering Projects. Open Journal of Social Sciences,03,30-34. doi: 10.4236/jss.2015.33007