Based on the test results of Lize navigation-power junction construction diversion through the normal fix-bed model with the scale of 1:100, the navigation flow condition in each construction diversion period is studied. There are a lot of problems in the first construction diversion period, such as excessive flow velocity, poor flow pattern, low navigation discharge and so on. To solve these problems, the comprehensive engineering measures for improving the navigation flow condition during construction are put forward. Among them, the structure forms of construction diversion cofferdam are optimized. Finally, the highest safe navigation discharge and reasonable navigation route are proposed. The experimental results obtained from the optimization scheme of the first construction diversion period are better than these from the original scheme in terms of flow velocity, flow pattern and so on. The research results may serve as reference for similar engineering.
In recent years, many scholars have made some studies of the navigation flow condition. According to the construction diversion model test results of Zhuzhou Navigation-power junction, Lun Chao Huang [
During the construction diversion period of navigation-power junction, cofferdam and diversion structures will narrow beam reach and reduce section area of water, change the original flow characteristics, thus affecting the river flood capacity and navigation flow condition. In order to ensure the safety of construction and the development of regional economy, it is necessary to ensure that the current condition of the river in the construction period can satisfy the safe navigation of the ship. This paper according to the normal physical model test of Lize navigation-power junction, analyses the existing problems, and puts forward the corresponding improvement measures.
Lize navigation-power junction is a comprehensive utilization of navigation-power junction, the construction period is long, the construction layout is complicated, and the construction process includes four dry seasons and four flood season. The four phase of the construction diversion period does not carry out the navigation requirements, so this paper mainly studies the navigation flow conditions during the three phase of the construction period. The construction diversion program adopted in this project: During the first dry period, the ship lock and 6.5 hole gate lock will be surrounded in the left, the fluid passed through the right bank and dismantled the starter cofferdam before the flood season. During the first flood period, the ship lock in continue to construction with the cofferdam protection for the whole year, the fluid passed through the right bank and the repaired 4 hole gate locks. During the second dry period, the power plant in the right will be surrounded, the ship lock will be in continue to construction in the left, the fluid passed through the middle bank and 4 hole gate locks. During the second flood period, the ship lock will be used for navigation, and the fluid will pass through foundation pit of the power plant. During the third dry period, the power plant in the right and the rest of 7.5 hole gate locks are surrounded, the fluid passed through 6 hole gate locks. During the third flood period, the power plant will be in continue to construction, the fluid will pass through 12 hole gate locks.
The recommended diversion standard for the construction period of the project: The dry season cofferdam flood standard is 10 years return period from November to April, and the corresponding design flux Q = 2620 m3/s. The flood season cofferdam flood standard is 10 years return period of the whole year, and the corresponding design Q = 20,500 m3/s.
In order to meet the requirements of the research content and reduce model scale effect, and make the research problem directly reflect the actual situation of the project construction period, the model is designed according to the gravity similarity criterion, and the normal solid model is adopted. The geometric scale of the normal model is 1:100. The simulation range is from the dam axis above 1.7 km to the dam axis below 1.3 km, and the navigation problems of the river reach in the period of the cofferdam construction are studied. The each scale of the model can be seen in
1) Water surface verification
This paper uses the water level gauge section of the field data to verify the accuracy of the model with the flux Q = 2300 m3/s and Q = 5260 m3/s. And the water level of the model is compared with the measured water level of the prototype. The results are shown in
According to the water level deviation values from
Name | Relational formula | Value |
---|---|---|
Geometric scale | 100 | |
Velocity scale | 10 | |
Discharge scale | 100,000 | |
Bed Roughness scale | 2.15 | |
Water flow time scale | 10 |
The maximum deviation occurred in the No. 3 section of the left bank and the No. 4 section of the right bank, where the measured values were 205.17 m and 208.68 m and the corresponding calculated values are 205.34 m and 205.58 m. The difference between the two was 0.17 m and 0.10 m. It shows that the model of the river channel and the prototype channel basically meet the requirements of similar resistance.
2) Velocity verification
This paper uses the draft water velocity field data to verify the accuracy of the model with the flux Q = 2600 m3/s. And the water velocity of the model is compared with the measured water velocity of the prototype. The results are shown in
As shown in
The hydraulic calculation index of the first stage cofferdam construction diversion is shown in
The layout of original scheme in the first construction diversion cofferdam period is shown in
In order to know the navigation flow condition of the right channel, the relevant data in engineering reach, such as water level, flow rate and flow pattern, are analyzed deeply. The results are shown in
The water retaining cofferdam is arranged in the left bank in the dry season, it reduces the flow area of the reach, and to a certain extent, the original river bed form and flow characteristics of the engineering reach have been changed. From
The dry cofferdam of left bank will be demolished in flood season. When Q = 4300 m3/s, the water ratio dropped to 0.34 per thousand, the maximum flow velocity is 2.46 m/s; When Q = 6750 m3/s, the river water ratio dropped to 0.42 per thousand, the maximum surface velocity is 2.75 m/s. When Q > 6750 m3/s, the maximum surface flow rate is generally more than 3 m/s, the engineering reach cannot meet the requirements of navigation.
The major measures taken in modification scheme are: The two section of the original scheme is connected to one section of the cofferdam in dry season. It reduces the backflow phenomenon produced at the corner of the two section cofferdam. The ends of annual cofferdam of the ship lock are designed as 1/4 elliptic curve, and its elliptic equation is x2/102 + y2/202 = 1. The modified dike head reduces the effect of the flow on the head of the cofferdam and the flow regime is relatively flat. The specific modification scheme layout is shown in
After the modified scheme of the first dry season, when Q ≤ 2620 m3/s, compared with the original plan, the maximum surface flow velocity of the revised plan is decreased. The overall flow pattern is better than the original plan. For example, the changes of velocity between the original scheme and modified scheme when Q = 1260 m3/s is shown in
After the modified scheme of the first flood season, when Q ≤ 6750 m3/s, the navigation flow condition of the engineering reach is better than that of the original scheme. For example, the maximum flow velocity in the engineering reach when Q = 6750 m3/s is shown in
1) The model has good similarity with the prototype, which can reflect the flow characteristics of the test section, and meet the requirements of the relevant standards.
Q (m3/s) | Upstream level (m) | Downstream level (m) | Average velocity (m/s) |
---|---|---|---|
2620 | 208.17 | 206.00 | 4.12 |
20,500 | 221.00 | 219.80 | 5.38 |
Construction period | Q (m3/s) | Vmax (m/s) | J (‰) |
---|---|---|---|
Dry season | 1260 | 2.50 | 0.52 |
1690 | 2.98 | 0.59 | |
1960 | 3.30 | 0.66 | |
2620 | 3.43 | 0.58 | |
Flood season | 4300 | 2.46 | 0.34 |
6750 | 2.75 | 0.42 | |
10,600 | 3.42 | 0.47 | |
16,400 | 3.80 | 0.47 | |
20,500 | 4.08 | 0.47 |
2) Through a comprehensive analysis of the navigation flow condition of Lize navigation-power junction, in view of the river bed of the first construction diversion period is narrow and the velocity changes greatly, the
navigation section of the construction period should be used as a navigation control section. And one-way traffic should be implemented.
3) The maximum navigation discharge of Lize navigation-power junction in the first construction period is Q = 1260 m3/s in dry season and Q = 6750 m3/s in flood season.
Kai Chen, (2016) Test Study on Navigation in the First Construction Period of Lize Navigation-Power Junction. Engineering,08,332-338. doi: 10.4236/eng.2016.86030