Technology transfer in the international construction industry is an important source as it helps companies move to better stages of design and construction capabilities. Three main barriers of technology transfer in construction have been identified through literature review—language barrier, cultural barrier and procurement options. The importance of these barriers has been identified through survey in the construction industry in Iran and Malaysia. 102 responses were received. Through SPSS analysis, the impacts of these barriers have been identified. The impact percentages are: language barrier 12.1%, cultural barrier 52.8% and procurement options 88.3%. Future researches are required in procurement options particularly in developing countries.
Technology transfer is an important element of relationship among construction companies, especially in the international construction industry. Further, transfer of technology in construction is a source of creativity that makes the company designs and constructs with new technologies. Then the companies are expected to transform and improve the current stage of technologies to the better stages. The process of technology transfer is based on the value and protection of products. It also includes several specific physical processes, systematic methods and managerial arrangements for functioning of the transformation [
The objective of this research is to verify the importance of technology transfer in international construction and investigate the impact of three main barriers of technology transfer in the Malaysia construction industry and the Iranian construction industry. The three main barriers identified through literature review are: language barrier, cultural barrier and procurement options.
Kumaraswamy and Shrestha [
The language barrier has been existed for many years in different sectors in many countries. In the construction industry, employers expect foreign labour to fulfil important needs of construction works due to the lack of local work force. Language barriers make additional complications and misunderstanding in the work place. Workers might pretend that they understand what is being said, but actually they do not fully understand what is being said. This situation can endanger some jobs. All language barriers may not have such direct consequences, but it can affect lack of productivity and lack of trust between the employer and workers which could be avoided if communication is clear. Trajkovski and Loosemore [
Another main issue of technology transfer which has been existed for long time is cultural differences. The importance of cultural differences is more critical for companies operating in international markets or having employees from different cultures. Ankrah and Proverbs [
Four principal procurement options in construction are discussed here. These are design-bid-build, design-build, public private partnership/private finance initiative (PPP?PFI) and partnering.
Design-bid-build has been one of the principal methods of delivery systems for the past few decades. Design bid build separates the design and construction duties. Many owners of the projects have faced diversity of disap- pointments using this system. The barriers of this procurement method to technology transfer are:
・ In Design-bid-build all the design procedure must be completed before tendering stage, leading to longer process duration.
・ Technological and programmatic obsolescence can put the owner in difficulty of transferring programmatic and technological changes.
・ Design-bid-build creates more adversarial relationships between the projects participants (designer, owner and contractor) rather than team work and cooperation.
・ As the owner is responsible for design, issues related to design change and construability can arise easily.
In the last half of the 20th century, the interest in non-traditional construction procurement method grew as clients demanded quicker delivery times and earlier knowledge of construction costs. One of the most popular alternatives to design bid build is design build project delivery method. Combination of both design and con- struction leads to fast track of projects. However there are some legal problems in using this procurement method, consequently in technology transfer. These are:
・ In design/build the clients have less input in proposed design since both the designer and the contractor belong to the same company or consortium.
・ Licensing or procurement laws or regulations might affect design/build as it might be limited or restricted to use this procurement method.
・ Selection of this process is considered as a complicated and time consuming method in public contracts. This is due to precise procedures and requirements of public contract to bring fair conditions and open competi- tions.
Public private partnership/private finance Initiative (PPP/PFI) has been contributed to the improvement of infrastructure projects and public services. In PPP/PFI delivery methods, the contractor not only design and build but also finance and operate the public facilities for a concession period. The barriers of this procurement method to technology transfer are:
・ The cost of finance is quite high, which can be a burden to private companies.
・ The government has explicit and implicit contingent liabilities that may arise due to loan guarantees provided to lenders and default of a private entity on non-guaranteed loans.
・ The costs of tendering in PPP/PFI projects are very high.
・ Contracts are brought about through complicated negotiations.
・ There are variety problems between the private sector and public sector related to different kinds of decision making, accountability and operations.
There has been a remarkable development in construction industry by using various partnering models since late 1980’s. This has been considered as a significant principal management strategy to develop organizational relations and project performance. Partnering has contributed to the effect to increase satisfaction and mutual benefits to client, consultants and contractors [
・ Misunderstanding of Partnering Concept: The main thing, while doing the partnering process, is to understand the process, if not this can come out as a critical issue.
・ Relationship problems: The main target of partnering is to motivate the participants to change their competi- tive attitudes to more cooperative and more team-oriented ones. The attitude of competitiveness in a business relationship may prohibit a good relationship between the contract partners.
・ Distrust: Trust is an essential element in a business relationship, but is very difficult to create. Without the key element of trust, it is almost impossible to create a win-win situation between the two parties.
・ Failure of risk sharing: A successful partnering can be easily threatened by failure of risk sharing. The main issue occurs when the participants of the project face problems to distribute the risk of the partnering process equally.
The total number of 102 from 300 questionnaires was returned, making the response rate33%. To increase the response rate, the questionnaires were distributed manually and collected later manually. The participants of the survey include architects, engineering consultants, quantity surveyors, contractors and construction managers as shown in
Reliability tests in the independent variables and dependant variables are conducted. Cronbach’s Alpha was calculated. To have the reliable variables, Cronbach’s Alpha coefficient needs to reach 0.7 for a reliable internal consistency. As it shown in
As can be seen from
Three hypotheses have been developed in relation to barriers to technology transfer in construction projects. These hypotheses have been evaluated from the analysis of the survey outcomes. Both null and alternative hypothesis are considered.
Hypothesis 1:
Ha1: There is a significant relation between language barriers and technology transfer in construction projects.
Ho1: There is no significant relation between language barriers and technology transfer in construction projects.
After doing a regression test, as it shown in
Responses | Percentage | |
---|---|---|
Engineering consultants | 58 | 57% |
Contractors | 17 | 17% |
Construction managers | 12 | 12% |
Architects | 10 | 10% |
Quantity surveyors | 5 | 5% |
Total | 102 | 100% |
Variables | Cronbach’s Alpha | Number of Items |
---|---|---|
Language Statistics | 0.720 | 2 |
Culture Statistics | 0.686 | 5 |
Procurement Statistics | 0.818 | 12 |
Technology Transfer Barriers Statistics | 0.773 | 2 |
From Experience, Technology Transfer in International Construction Are: | ||||
---|---|---|---|---|
Minor Issues | Average Issues | Serious Issues | Total | |
Iranians | 6 (14.6%) | 19 (46.3%) | 16 (39%) | 41 |
Malaysians | 3 (5.7%) | 27 (50.9%) | 23 (43.4%) | 53 |
9 (9.6%) | 46 (48.9%) | 39 (41.5%) | 94 |
sis is rejected and the alternative hypothesis in accepted. The R-square is 0.121 so it has 12.1 percent impact as a barrier in construction projects in technology transfer.
Hypothesis 2
Ha2: There is a significant relation between cultural barriers and technology transfer in construction projects.
Ho2: There is no significant relation between cultural barriers and technology transfer in construction projects.
As can be observed from
Hypothesis 3
Ha3: There is a significant relation between procurement option barriers and technology transfer in construction projects.
Ho3: There is no significant relation between procurement option barriers and technology transfer in construction projects.
According to
Through this research, the importance of technology transfer in international construction has been verified.
Model | R | R Square | Adjusted R Square | Change Statistics | ||||
---|---|---|---|---|---|---|---|---|
R Square Change | F Change | df1 | df2 | Sig. F Change | ||||
1 | 0.348a | 0.121 | 0.103 | 0.121 | 6.808 | 2 | 99 | 0.002 |
Model | Sum of Squares | df | Mean Square | F | Sig. |
---|---|---|---|---|---|
Regression | 3.491 | 2 | 1.745 | 6.808 | 0.002b |
Residual | 25.382 | 99 | 0.256 | ||
Total | 28.873 | 101 |
aDependent Variable: Tech_transfer_barrier. bPredictors: (Constant), Foreign supervisor faces language problems, Communication in multi-cultural construction sites is made even more complicated.
Model | R | R Square | Adjusted R Square | Change Statistics | ||||
---|---|---|---|---|---|---|---|---|
R Square Change | F Change | df1 | df2 | Sig. F Change | ||||
1 | 0.727a | 0.528 | 0.503 | 0.528 | 21.473 | 5 | 96 | 0.000 |
Model | Sum of Squares | df | Mean Square | F | Sig. |
---|---|---|---|---|---|
Regression | 15.243 | 5 | 3.049 | 21.473 | 0.000b |
Residual | 13.630 | 96 | 0.142 | ||
Total | 28.873 | 101 |
aDependent Variable: Tech_transfer_barrier. bPredictors: (Constant), Lack of continuous, open and honest communication, Unfair sharing of risks or rewards among the client and the project participants, Understanding the culture of staff from different countries, Cultural differences for companies operating in international markets, is critical, Unsolved arguments.
Model | R | R Square | Adjusted R Square | Change Statistics | ||||
---|---|---|---|---|---|---|---|---|
R Square Change | F Change | df1 | df2 | Sig. F Change | ||||
1 | 0.940a | 0.883 | 0.867 | 0.883 | 54.645 | 12 | 87 | 0.000 |
Model | Sum of Squares | df | Mean Square | F | Sig. |
---|---|---|---|---|---|
Regression | 25.171 | 12 | 2.098 | 54.645 | 0.000b |
Residual | 3.339 | 87 | 0.038 | ||
Total | 28.510 | 99 |
aDependent Variable: Tech_transfer_barrier. bPredictors: (Constant), High cost of tendering in PPP/PFI projects, Procurement laws and regulations negatively effect in design/build contract, Changes in design during construction, Local partners (companies) have no input on design in design/build contract, Partners failed to build a trust relationship, Unnecessary interference from government for PPP/PFI projects, Partners failed to share information, PPP/PFI contracts create/required complicated negotiations, Long process in design procedure in design-bid-build, Too long term concession period for PPP/PFI projects, Partners' lack of win-win attitude, Misunderstanding/conflict due to laws and regulations of local government
*Corresponding author.
Byung Gyoo Kang,Mehrdad Arefi,Boon Hoe Goh,Myung Kyu Song, (2015) An Investigation into Barriers of Technology Transfer in the Construction Industry in Iran and Malaysia. Open Journal of Social Sciences,03,85-91. doi: 10.4236/jss.2015.37015