Energy and Power Engineering, 2013, 5, 1198-1201
doi:10.4236/epe.2013.54B227 Published Online July 2013 (http://www.scirp.org/journal/epe)
Research on the Fault Location Principle for the Earthing
Electrode Line of the UHVDC Transmission System
Xu Peng, Yu Jiang
CSG Power Dispatching Control Center, Guangzhou, China
Email: xupeng2@csg.cn
Received February, 2013
ABSTRACT
The UHVDC transmission line transports large-capacity power, and its safety operation has very important rule on the
safe operation of grid. Currently, in the DC transmission system, the earthing electrode line has th e functions of ground
potential fixing and bipolar imbalance current circulation during the operation of bipolar balance. Therefore the moni-
toring to the earthing electrode line operation is very essential. This article firstly introduced the curren t situation of the
research on the earthing electrod e line fault locatio n method, then bu ilt the relevant PSCAD/EMTDC model for simula-
tion verification of the current using Time Domain Reflectometry for the UHVDC earthing electrode line, and at last
analyzed the reasons for the formation of the blind monitoring zones.
Keywords: Earthing Electrode Line; Pulse Reflection Method
1. Introduction
The earthing electrode system of the DC transmission
system could be divided into three parts: the neutral bus
of the converter station, the earthing electrode line, and
the earthing electrode. Currently, UHVDC systems put
into operatio are majority DC double-end transmission
system, which has only one transmitting end and one
receiving end. Figure 1 shows the structure of the earth-
ing electrode system of the double-end UHVDC trans-
mission project [1].
The line connection modes of the UHVDC transmis-
sion system are:The bipolar (BP) mode;The mono-
pole ground return (GR) mode;The monopole metallic
return (MR) mode; and The open line test (OLT)
mode. Among which, the mode is only single-point
earthing, and there is no current in the ground, so the
earthing electrode only has the function of clamping the
Figure 1. Structure of the earthing electrode system.
neutral point potential, while in the mode , , and
the earthing electrode not only clamps the neutral
point potential, but also provides a pathway for the DC
current. Therefore the characteristics of the earthing
electrode system in the ways , , and need to be
investigated in particu larly.
The GR and OLT modes form a circuit with the
ground via a high voltage DC line, and therefore the cur-
rent flowing in the earthing electrode and the earthing
electrode line is equal to the curren t on the line.
The BP mode is the normal operation way of the
UHVDC, the earthing electrode line only has the func-
tions of ground potential fixing and bipolar imbalance
current circulation, but the fault of the earthing electrode
line would still h ave great impact on the safe and reliable
system operation. One is if the earthing electrode line has
fault or the working status is not clear, then the system
could not convert fro m the balance oper ation mode to the
unbalanced operation mode in a safe and reliable manner.
The other is the fault of the earthing electrode line might
also cause communication disturbance to the nearby
communication facilities, and result in personnel injuries
or corrosion of the metal equipment at the fault lo cations.
So, when the DC transmission line running with BP
mode, the monitoring of the earthing electrode line is
very essential. [2]
2. Research on the Fault Location Principle
of the Earthing Electrode Line
Copyright © 2013 SciRes. EPE
X. PENG, Y. JIANG 1199
2.1. The Research on the Fault Location
Principle of the Earthing Electrode Line
When the DC system runs in BP mode, the imbalance
current flowed through the earthing electrode line is very
few, which is usually no more than 1% of the system
rated current; also the voltage at the outlet end of the
earthing electrode line (end of the converter station) is
only a dozens of volts, which makes it difficult for the
fault monitoring of the earthing electrode line running
under the BP mode.
Currently, th e fault location principles in the applica-
tion of the HVDC and UHVDC earthing electrode line
have the impedance method (ABB) [3] and the Time
Domain Reflectometry (SIMENS) [4]. As the impedance
method is unable to determine the fault type and fault
location, have the disadvantages of unwanted action or
refusing action and the settin g valu es are great in fluen ced
by the earthing transition resistance, so the existing
UHVDC transmission system is widely using the Time
Domain Reflectometry.
2.2. Time Domain Reflectometry
Based on the theory of long distance transmission line,
the Time Domain Reflectometry [5] is a type of line
monitoring method to determine the fault location, ac-
cording to the amplitude, polarity, arrival time, or other
electrical signals of the reflected pulse on the conductor
which detected by inputting a high frequency pulse sig-
nal to one end of the conductor [6-8]. Figure 2 shows
different characteristics between normal and abnormal.
The basic principle of the Time Domain Reflectometry
[9-10] which applied to the earthing electrode line is as
follows: apply the first voltage pulse at the side of the
end of the converter station of the earthing electrode line
and on the earthing electrode line at the same time, the
pulse goes through the earthing electrode line and is re-
flected when reaching the earthing electrode. Take the
record of the voltage wave on the line at the applying
position of the pulse, and when recording the reflected
wave at the end of the earthing electrode line, apply the
Figure 2. The Time Domain Reflectometry principle.
second pulse. Repeat the above processes until the fault
of the line and receiving the “extra” reflected wave. If the
earthing electrode line has fault, the fault poin t will form
a wave impedance singularity, which is a reflection point
for the pulse in addition to the earthing electrode, and by
the reflection of the pulse at this location, a measurable
reflected pulse in addition is generated. After receiving
this reflected pulse, stop to apply the monitoring pulse.
The reflected pulse at the fault point arrives at the pulse
applying point earlier than the reflected pulse at the end
of the earthing electrode line, and according to the return
time of the reflected pulse at the fault point and wave
velocity, the distance between the fault point and the
monitoring point is determined as
/
1
lv
2
t
(1)
3. Simulation Verification
In order to verify the correctness and the validity of the
Time Domain Reflectometry proposed in this article, the
simulation model of the ±800kV UHVDC transmission
system is established by using the PSCAD/EMTDC
electromagnetic transient simulation software, which is
shown in Figure 3.
Figure 4 shows the line parameters of the earthing
electrode line of UHVDC transmission.
Figure 3. Simulation model of the ±500 kV HVDC trans-
mission system.
Figure 4. Model of the e arthing electrode line.
Copyright © 2013 SciRes. EPE
X. PENG, Y. JIANG
1200
Normal line Single-line earthing short circuit fault
Double-line earthing short circuit fault Double-line short circuit fault
Single-line disconnection fault Double-line disconnection fault
Figure 5. Results of the PSCAD/EMTDC simulation for
various fault types.
Transmit a pulse with amplitude U = 150 V and pulse
width tp= 30 µs at the start side of the earthing electrode
line at 1s (2s as a cycle). Figure 5 shows the PSCAD/
EMTDC simulation results of the pulse on the earthing
electrode line when the different fault types occured at
the neutral point of the UHVDC earthing electrode line.
It is conclued from Figure 5: polarities of the reflec-
tion pulse and the transmission pulse under disconnection
fault is same, while under earthing faul is opposite, and
the fault type of the earthing electrode line could be de-
duced based on the polarity of the reflection pulse.
For the metallic short circuits of the earthing electrode
line happed at different locations and different types, this
article also made the PSCAD/EMTDC simulation, take
the sampling frequency fs = 100 kHz, v = 2.97×108 m/s.
The fault location is shown in Table 1.
The simulation result in Table 1 shows, in the case of
metallic faults, there are certain blind detection zones at
the start side (transmission side) and the end side of the
line; and the longer the fault distance, the bigger the fault
location error sh ows. Within the range of 25% to 75% of
the line, the maximum actual error and the maximum
relative error of the fault location are 2.042 km and
1.442% in separately.
Reasons for the occurred detection blind zones:
1) As shown in Figure 6, the transmission pulse can
not separated from the reflection pulse at the start side
fault. The reason is, the transmission pulse itself occupies
a certain period of time, when the fault point is very
close by, the reflection pulse shows almost simultane-
ously with the transmission pu lse, as the amp litud e of the
transmission pulse is large and also exist when the line
has no short circuit, and therefore the transmission pulse
can not separated from the reflection pulse by fault near
by the start side, also the fault location of the start side
could not be identifi e d.
As shown in Figure 7, the reflection pulse at the end
side fault can not separated from the fixed reflection
pulse of the earthing electrode resistance. This is because
when the fault point at the end side is very close to the
earthing electrode resistance, the reflection pulse by fault
also shows up almost simultaneously with the fixed re-
flection pulse and with almost equal amplitude, the two
reflection pulses are superimposed, and therefore the
reflection pulse at the end side fault can not separated
from the fixed reflection pulse of the earthing electrode
resistance, also the fault location of the end side could
not be identified.
Table 1. Results of fault location under metallic faults (km).
Method of the article
Fault typeFault
location Simulation
result Actual error Relative error
2% Can not
identified Can not
identified Can not
identified
25% 47.52 0.309 0.655%
50% 93.555 -0.867 0.918%
75% 139.59 -2.042 1.442%
Single-line
short cir-
cuit
earthing
98% Can not
identified Can not
identified Can not
identified
2% Can not
identified Can not
identified Can not
identified
25% 47.52 0.309 0.655%
50% 93.555 -0.867 0.918%
75% 139.59 -2.042 1.442%
Dou-
ble-line
short cir-
cuit
earthing
98% Can not
identified Can not
identified Can not
identified
Figure 6. Single-line short circuit earthing (lF=2%l).
Copyright © 2013 SciRes. EPE
X. PENG, Y. JIANG
Copyright © 2013 SciRes. EPE
1201
Figure 7. Double-line short circuit earthing (lF = 98%l).
4. Summary
Aiming at the current situation that the Time Domain
Reflectometry is used for fault location of the earthing
electrode line of the UHVDC system, this article de-
scribed the principle of the Time Domain Reflectometry,
established corresponding PSCAD/EMTDC model for
simulation verification, analyzed the error precision of
the Time Domain Reflectometry, pointed out the reasons
for the formation of the monitoring blind zones, and con-
structed the foundation for the further study of the fault
location principle of the earthing electrode line of the
UHVDC transmission system.
REFERENCES
[1] DC transmission Scientific Research Group of Power
Generation Teaching and Research Center of Zhejiang
University, “DC transmission,” Beijing, Publishing house
of electric power industry, 1982, pp. 6-8.
[2] W. J. Zhao, “HVDC Transmission Engineering Technol-
ogy,” Beijing: China Electric Power Publishing House,
2007, pp.1-3.
[3] Nanjing Nari-relays Electric Co., Ltd., “Design Specifica-
tion for Earthing Electrode Line Monitoring,” 2009.
[4] “Maintenance Manuals of Electrode Line Monitor-
ing,”Siemens, 2007.
[5] Y. S. Gong, Z. Z. Li and C. Y. Li, “Evapotranspiration
Assessed According to Soil Water Content Measured by
the Time Domain Reflectometer,” Journal of applied me-
teorological science,Vol. 9,No. 1,1998, pp.72-78.
[6] Q. Meng, “Research Development and Its Application in
the Irrigation of the Time Domain Reflectometer,” Water
Saving Irrigation, 1999, pp.1-3.
[7] S. D. Logsdon, “Effect of Cable Length on Time Domain
Reflectometry Calibration for High Surface Area Soils,”
Soil Science Society America, Vol. 64, No. 1, 2000, pp.
54-61. doi:10.2136/sssaj2000.64154x
[8] W. F. Kane, “Monitoring Slope Movement with Time
Domain Reflectometry,” Applications for Engineers and
Geologists, 2000, pp.1-8.
[9] J. Ammon, G. Plewka and G. Schaller, “Method and De-
vice for the Electrical Monitoring of An Electrode Lead
of A Bipolar HVDC Transmission System,” US Pat ent
No.6518769 B1, 2003
[10] G. Asplund, “Electrode Line Protection,” US Patent No.
5117323,1992